Engineering works, purchase, construction and commissioning of the Base Oil Hydrocracking Project for LOTOS OIL
Projects

Engineering works, purchase, construction and commissioning of the Base Oil Hydrocracking Project for LOTOS OIL

Total area: 5 000, 1 000 m2
Contract Value: PLN 19.75 million PLN netto
Deadline for completion: November, 2023

On February 27th 2023, Mostostal Płock and Naftoremont - Naftobudowa signed an agreement for engineering, purchase, construction and commissioning of the Base Oil Hydrocracking Project for LOTOS OIL sp. z o.o.

The subcontract includes the prefabrication and assembly of 4 tanks (2 tanks of 5,000 m3 and 2 tanks of 10,000 m3).

Details of the concluded contract

Deadline for completion and settlement of the contract: 29 weeks from the date of handing over the foundation of the last tank, which should take place no later than April 20, 2023.
Contract value: PLN 19.75 million PLN netto
Warranty period for the works performed and the materials used: 39 months.