Engineering works, purchase, construction and commissioning of the Base Oil Hydrocracking Project for LOTOS OIL

Tank capacity: 5 000, 1 000 m3
Contract value: PLN 19.75 million PLN netto
Completion date: November, 2023

On February 27th 2023, Mostostal Płock and Naftoremont - Naftobudowa signed an agreement for engineering, purchase, construction and commissioning of the Base Oil Hydrocracking Project for LOTOS OIL sp. z o.o.

The subcontract includes the prefabrication and assembly of 4 tanks (2 tanks of 5,000 m3 and 2 tanks of 10,000 m3).

Details of the concluded contract

Deadline for completion and settlement of the contract: 29 weeks from the date of handing over the foundation of the last tank, which should take place no later than April 20, 2023.
Contract value: PLN 19.75 million PLN netto
Warranty period for the works performed and the materials used: 39 months.

Selected projects